3) A company dedicated to the manufacture of wooden figures receives orders A, B, C, D, E and F during the beginning of the week

3) A company dedicated to the manufacture of wooden figures receives orders A, B, C, D, E and F during the beginning of the week and in the order presented in the table. This company only

has a laser cutting machine for which it will be necessary to give priority to the different jobs. You are called to carry out said order of priorities and thus optimize work times.

The following table shows the data required for each job.

Job |Processing time (days) |Deadline (days left) A | 4 | 20 B |12 | 30 C |2 |15 D |11 |16 E |10 |18 F |3 |5 G |6 |9

Through the use of FCFS and SOT techniques, obtain:

a) Quantity and name of the tasks that are completed on time. b) Show the average delay time, total and average transit time. c) Compare both priority techniques and comment on which is more effective for the case, justify.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management In The Hospitality Industry

Authors: Mike Olsen, Michael D Olsen

2nd Edition

0471292397, 9780471292395

More Books

Students also viewed these General Management questions

Question

Solve the matrix equation AX = b for the vector X in the following:

Answered: 1 week ago

Question

3. Im trying to point out what we need to do to make this happen

Answered: 1 week ago