3 . A pattern of trenches has to be planned, marked out, dig and filled with concrete made from dry ingredients which are to be
A pattern of trenches has to be planned, marked out, dig and filled with concrete made
from dry ingredients which are to be collected in the correct quantities from another
location. The activities involved together with their duration and manpower are as
follows:
Reference Activity Duration hours Men
A Plan layout
B Mark out site
C Dig trenches
D Obtain concrete material
E Mix concrete
F Fill trenches
a Draw an activity on arrow and an activity on node network of the project and
determine the critical path and minimum time it will take to complete the project.
b Construct a bar chart and determine the manpower requirements throughout the
project.
c Assuming that the digging equipment was taken in error by the vehicle collecting
the concrete material. Draw another activity on arrow diagram to show the
affect this would have on the completion of the project.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started