3. Regarding Liquidated Damages, all the following are correct EXCEPT : a) Must be a reasonable estimate of actual damages. b) May include punitive damages.
3. Regarding Liquidated Damages, all the following are correct EXCEPT:
a) Must be a reasonable estimate of actual damages.
b) May include punitive damages.
c) May be a fixed amount or formula.
d) Must be agreed to by both parties.