3) Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. Activity Normal Time Normal Cost

image text in transcribed
3) Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. Activity Normal Time Normal Cost Crash Duration Crash Cost X 8 days $6,000 6 days $8,000 Y 3 days $1,800 2 days $2,400 Z 12 days $5.000 9 days $7,700 a. What is the crash cost per unit time for each of the three activities? b. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost? 3) c. Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Marketing

Authors: Nigel Piercy and David Cravens

10th edition

78028906, 978-0078028908

More Books

Students also viewed these General Management questions

Question

part 2 of lab using pyrhon converting Celsius to farenhheit

Answered: 1 week ago