3D Meule Screenshot My Add-ins dels @ Number Using the City of Mankato Carney Avenue TH 66 Turnback project plans, determine the most likely cost and the quantity of the following items: 2.5 "Asphalt Concrete - units of SY Curb & Gutter - units of LF Prepare your bid cost using the RS Means 2002 information provided by the instructor. Because these are not current costs, you will need to raise them via inflation to 2021 costs - use (F/P, 3%, 19) or the formula to adjust costs. Also, you will need to provide a location cost appropriate to Mankato. Use a location factor of 0.986 on all costs (Mankato). To submit your bid, provide estimated quantities, unit prices and total prices for each item, filling in the bid table below. Provide full back up of all cost and quantity determinations. Submit backup as a hard copy to receive full credit. Item Quantity Units Cost per Unit Total Cost 2.5 "Asphalt Concrete SY $ $ Curb & Gutter LF $ $ 3D Meule Screenshot My Add-ins dels @ Number Using the City of Mankato Carney Avenue TH 66 Turnback project plans, determine the most likely cost and the quantity of the following items: 2.5 "Asphalt Concrete - units of SY Curb & Gutter - units of LF Prepare your bid cost using the RS Means 2002 information provided by the instructor. Because these are not current costs, you will need to raise them via inflation to 2021 costs - use (F/P, 3%, 19) or the formula to adjust costs. Also, you will need to provide a location cost appropriate to Mankato. Use a location factor of 0.986 on all costs (Mankato). To submit your bid, provide estimated quantities, unit prices and total prices for each item, filling in the bid table below. Provide full back up of all cost and quantity determinations. Submit backup as a hard copy to receive full credit. Item Quantity Units Cost per Unit Total Cost 2.5 "Asphalt Concrete SY $ $ Curb & Gutter LF $ $