5.1 Consider the following project of Dladla Enterprises that comprise only the following three activities viz. Material, labour and transport. The costs are incurred when
5.1 | Consider the following project of Dladla Enterprises that comprise only the following three activities viz. Material, labour and transport. The costs are incurred when the work is performed but the cash flow depends on the timing of the income and expenses. The timing of the expenses are shown below: |
Expenses | March (R) | April (R) | May (R ) | Cash flow information |
Material (delivered to workshop) | 8 000 | 10 000 | - | Supplier gives one month |
Labour | - | 5 000 | 12 000 | Pay in the month of use |
Transport to site | - | - | 4 000 | Pay one month before work is performed |
The income from the client is a 40% mark-up of the expenses for each month and is received one month after the work is performed.
Required
Draw up a Cash budget of Dladla Enterprises for the period 01 March to 30 June 2018.
Note: For the month of June, only the receipts are required.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started