Question

1 Approved Answer

6. Planned project cost was $40 million and the contractor was able to complete the job for $4 1.5 million. The rate of the fixed

image text in transcribed

6. Planned project cost was $40 million and the contractor was able to complete the job for $4 1.5 million. The rate of the fixed fee is 200 and the rate ofthe save sharing is 10% (6pt) a. What is the amount of fee if this project is under the cost plus fixed fee plus profit-sharing contract? Please assume that the contractor offered guaranteed maximum price (GMP) of 42 million. Please show your calculation. b. What is the amount of fee if this project is under the cost plus sliding fee contract? Please show your calculation

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate accounting

Authors: J. David Spiceland, James Sepe, Mark Nelson

7th edition

978-0077614041, 9780077446475, 77614046, 007744647X, 77647092, 978-0077647094

More Books

Students also viewed these Accounting questions