7. EPC project has an original planned schedule of 15 months with a budget, excluding contingency, of $3,035,150. Below are update reports for the first 6 months of the project. Perform an earned-value analysis of the project. For each report period, calculate CV, SV, CPI, SPI, ETC, and EAC. In the table, Interpret CV, SV, SPI, AND CPI values. Status report for Planned Earned Actual month (BCWS) (BCWP) (ACWP) $3,850 $3,870 $3,986 2 $63,672 $62,932 $64,600 3 $284,904 $252,715 $291,429 4 $319,615 $310,303 $351,481 5 $579.343 $609,103 $643,818 6 $654,863 $657,780 $663,365 CPI 1.12 1.10+ 1.08 106 1.04 102+ 1 SPI 0186 0,88 0,90 092 094 0.96 0.98 1.0- 1102 1,04 1,06 1.08 1.0 1.12 1.14 -0.98 0.96 -0.94 0.92 -0.90-1 0.88 0.86 Project Performance - CPI and SPI Planned Earned Actual Status report for month Estimate to Complete ETC Estimate at Completion EAC Difference (BCWS) (BCWP) (ACWP) CV SV CPI SPI 1 2 3 4 5 6 7. EPC project has an original planned schedule of 15 months with a budget, excluding contingency, of $3,035,150. Below are update reports for the first 6 months of the project. Perform an earned-value analysis of the project. For each report period, calculate CV, SV, CPI, SPI, ETC, and EAC. In the table, Interpret CV, SV, SPI, AND CPI values. Status report for Planned Earned Actual month (BCWS) (BCWP) (ACWP) $3,850 $3,870 $3,986 2 $63,672 $62,932 $64,600 3 $284,904 $252,715 $291,429 4 $319,615 $310,303 $351,481 5 $579.343 $609,103 $643,818 6 $654,863 $657,780 $663,365 CPI 1.12 1.10+ 1.08 106 1.04 102+ 1 SPI 0186 0,88 0,90 092 094 0.96 0.98 1.0- 1102 1,04 1,06 1.08 1.0 1.12 1.14 -0.98 0.96 -0.94 0.92 -0.90-1 0.88 0.86 Project Performance - CPI and SPI Planned Earned Actual Status report for month Estimate to Complete ETC Estimate at Completion EAC Difference (BCWS) (BCWP) (ACWP) CV SV CPI SPI 1 2 3 4 5 6