8) Design a layout using the following information. There are 6 tasks with the following predecessor and time requirements: Task Predecessor Time Required (min) A

8) Design a layout using the following information. There are 6 tasks with the following predecessor and time requirements:

Task Predecessor Time Required (min)

A None 5

B None 7

C None 9

D None 3

E B, D 8

G A, C 10

You need to complete 40 items per each 10 hour day. Use the line balance technique you learned using the Longest Processing Time to answer the following questions:

What is the cycle time?Round down to nearest integer.

What is the theoretical minimum number of stations?Round up to the nearest integer

At what station will D be completed?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Management Science

Authors: Bernard W. Taylor

11th Edition

132751917, 978-0132751919

More Books

Students also viewed these General Management questions