8. Project Y has initial cost of $10,000, and the discount rate for each project is 12%. Expected cash flow is given below for project:
8. Project Y has initial cost of $10,000, and the discount rate for each project is 12%. Expected cash flow is given below for project:
Year Project Y 1
1 6500
3 5,000
4 3000
calculate NPV for this project