a . Assuming that the desired output is 6 0 customers per hour, what are the cycle time and minimum number of stations ( workers

a. Assuming that the desired output is 60 customers per hour, what are the cycle time and minimum number of stations (workers) needed?
Cycle time =60 customers/60 minutes =1 customer per minute =60 seconds
Minimum number of workers needed =(25+30+20+15+10+60)/60=160/60=2.66
The cycle time is 60 seconds and the minimum number of workers needed is 3.
b. Using cycle time of 60 seconds and Assign the task with the longest time heuristic rule, perform assembly line balancing for the cafeteria.
Station Time left Eligible Will fit Assign (time) Idle

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Project Management

Authors: Jack Gido, Jim Clements

4th Edition

9780324656152, 324656130, 978-0324656138

More Books

Students also viewed these General Management questions