A Case Study on Hershey's ERP Implementation Failure: The Importance of Testing and Scheduling Imagine waking up one day to find out that your company's

A Case Study on Hershey's ERP Implementation Failure: The Importance of Testing and Scheduling

Imagine waking up one day to find out that your company's supply chain has ground to a halt, making it impossible to fulfill $100 million worth of orders. For Hershey's confectionary manufacturing and distribution operations, this nightmare came true in 1999.

Overview - Hershey's ERP Implementation Failure

When it cutover to its $112-million IT systems, Hershey's worst-case scenarios became reality. Business process and systems issues caused operational paralysis, leading to a 19-percent drop in quarterly profits and an eight-percent decline in stock price.

Key Facts

Here are the relevant facts: In 1996, Hershey's set out to upgrade its patchwork of legacy IT systems into an integrated ERP environment. It chose SAP's R/3 ERP software, Manugistic's supply chain management (SCM) software and Seibel's customer relationship management (CRM) software. Despite a recommended implementation time of 48 months, Hershey's demanded a 30-month turnaround so that it could roll out the systems before Y2K. Based on these scheduling demands, cutover was planned for July of 1999. This go-live scheduling coincided with Hershey's busiest periods - the time during which it would receive the bulk of its Halloween and Christmas orders. To meet the aggressive scheduling demands, Hershey's implementation team used a direct implementation approach and had to cut corners on critical systems testing phases.

When the systems went live in July of 1999, unforeseen issues prevented orders from flowing through the systems. As a result, Hershey's was incapable of processing $100 million worth of Kiss and Jolly Rancher orders, even though it had most of the inventory in stock. This is not one of those "hindsight is 20-20" cases. A reasonably prudent implementer in Hershey's position would never have permitted cutover under those circumstances. The risks of failure and exposure to damages were simply too great.

ERP Systems Testing

Hershey's implementation team made the cardinal mistake of sacrificing systems testing for the sake of expediency. As a result, critical data, process and systems integration issues may have remained undetected until it was too late. Testing phases are safety nets that should never be compromised. If testing sets back the launch date, so be it. The potential consequences of skimping on testing outweigh the benefits of keeping to a longer schedule. In terms of appropriate testing, our firm advocates a methodical simulation of realistic operating conditions. The more realistic the testing scenarios, the more likely it is that critical issues will be discovered before cutover.

Question:

image text in transcribed

Based on the conditions of the Hershey project, make an analysis based on the 5 stop test criteria above. Have all the criteria been met? If not, which criteria have not been met and provide reasons.

All planned tests executed and passed All coverage goals met Stop Test Detection of specific number of defects Rates of defect detection fallen below a specified level Fault seeding ratios are favorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Handbook Of Database Security Applications And Trends

Authors: Michael Gertz, Sushil Jajodia

1st Edition

1441943056, 978-1441943057

More Books

Students also viewed these Databases questions

Question

a. Do team members trust each other?

Answered: 1 week ago

Question

a. How will the leader be selected?

Answered: 1 week ago