A company budgets production of 15,000 solar panels in July. Each unit requires 4 hours of direct labor at a rate of $20 per hour.
A company budgets production of 15,000 solar panels in July. Each unit requires 4 hours of direct labor at a rate of $20 per hour. The cost of direct labor for July is:
Multiple Choice
-
$600,000.
-
$300,000.
-
$1,200,000.
-
$1,500,000.
-
$960,000.