A company is to carry out a major modernization of its factory commencing in two weeks, time. During the modernization, which is expected to take

A company is to carry out a major modernization of its factory commencing in two weeks, time. During the modernization, which is expected to take four weeks to complete, no production of the companys single product will be possible.
The following additional information is available:
Sales/Debtors: Demand for the product at 100 per unit is expected to continue at 800 units per week, the level of sales achieved for the last four weeks, for one further week. It is then expected to reduce to 700 units per week for three weeks, before rising to a level of 900 units per week where it is expected to remain for several weeks. All sales are on credit, 50 per cent being received in cash in the week following the week of sale and 50 per cent in the week after that.
Production/Finished goods stock (inventories): Production will be at a level of 1,200 units per week for the next two weeks. Finished goods stock is 2,800 units at the beginning of week 1
Raw material stock: Raw material stock is 36,000 at the beginning of week 1. This will be increased by the end of week 1 to 40,000 and reduced to 10,000 by the end of week 2.
Costs
Cost information
( per unit)
Variable:
Raw material
35
Direct labour
20
Overhead
10
Fixed:
Overhead
25
Fixed overheads have been apportioned to units on the basis of the normal output level of 800 units per week and include depreciation of 4,000 per week.
In addition to the above unit costs, overtime premiums of 5,000 per week will be incurred in weeks 1 and 2. During the modernization variable costs will be avoided, apart from direct labour which will be incurred at the level equivalent to 800 units production per week. Outlays on fixed overheads will be reduced by 4,000 per week.
Payments: Creditors for raw materials, which stand at 27,000 at the beginning of week 1, are paid in the week following purchase. All other payments are made in the week in which the liability is incurred.
Liquidity: The company has a bank overdraft balance of 39,000 at the beginning of week 1 and an overdraft limit of 50,000.
The company is anxious to establish the liquidity situation over the modernization period, excluding the requirements for finance for the modernization itself.
Required:
(a) Prepare a weekly cash budget covering the six-week period up to the planned completion of the modernization. (20 marks)
(b) Comment briefly on any matters concerning the liquidity situation that you feel should be drawn to the attention of management (10 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Management Principles and Applications

Authors: Sheridan Titman, Arthur Keown, John Martin

12th edition

133423824, 978-0133423822

More Books

Students also viewed these Finance questions