Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A company is using a Kanban system with 3 containers, each holding 30 parts, between a downstream (using) and an upstream (producing) work center. The
A company is using a Kanban system with 3 containers, each holding 30 parts, between a downstream (using) and an upstream (producing) work center. The using work center can handle 300 jobs per day. The average elapsed time for the entire cycle is currently 0.25 days. The company is concerned about the safety factor for the operation. Which of the following is the safety factor () of the current operation? a. 90 percent b. 20 percent c. 17 percent d. 6 percent
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started