A company manufactures a product which requires four hours per unit of machine time. Machine time is a bottleneck resource as there are only ten
A company manufactures a product which requires four hours per unit of machine time. Machine time is a bottleneck resource as there are only ten machines which are available for 12 hours per day, five days per week. The product has selling price of $ 130 per unit, direct materials costs of $50 per unit, labour costs of $40 per unit and factory overhead costs of $20 per unit. These costs are based on weekly production and sales of 150 units.
What is the throughput accounting ratio?
A) 1.33
B) 2.00
C) 0.75
D) 0.31
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started