Question

1 Approved Answer

A company operates 25 days a month. The standard output per worker per day is 40 units. The company is using an exact demand

A company operates 25 days a month. The standard output per worker per day is 40 units. The company is using an exact demand strategy in its production plan. If the demand for next month is 20,000 units, how many workers that the company required to meet the demand?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To solve this problem we need to find the total output required per month and then calculate the num... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel,

7th Edition

470226218, 978-0470226216

More Books

Students also viewed these General Management questions

Question

Excel caculation on cascade mental health clinic

Answered: 1 week ago

Question

Which three organizations should you follow? Why?

Answered: 1 week ago