A company's construction time follows a normal distribution. The mean time to construct a building is 100 days and the standard deviation is 15 days.
A company's construction time follows a normal distribution. The mean time to construct a building is 100 days and the standard deviation is 15 days. The construction team will receive a penalty if completion of the job exceeds 110 days. What is the probability that they will receive a penalty?