A contractor has a job which should be completed in 100 days. At present, he has 80 men on the job and it is estimated
A contractor has a job which should be completed in 100 days. At present, he has
80 men on the job and it is estimated that they will finish the work in 130 days. Of the
80 men, 50 are each paid P120.00 a day, 25 at P180 a day, and 5 at P250 a day.
For each day beyond the original 100 days, the contractor has to pay P500
liquidated damages.
a. How many more men should the contractor add so that he can complete
the work on time?
b. If of the additional men, 2 are paid P180 a day, and the rest at P120 a day,
would the contractor save money by employing more men and not paying
the fine?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started