A contractor has a job which should be completed in 100 days. At present, he has 80 men on the job and it is estimated

A contractor has a job which should be completed in 100 days. At present, he has

80 men on the job and it is estimated that they will finish the work in 130 days. Of the

80 men, 50 are each paid P120.00 a day, 25 at P180 a day, and 5 at P250 a day.

For each day beyond the original 100 days, the contractor has to pay P500

liquidated damages.

a. How many more men should the contractor add so that he can complete

the work on time?

b. If of the additional men, 2 are paid P180 a day, and the rest at P120 a day,

would the contractor save money by employing more men and not paying

the fine?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Global Capitalism Its Fall And Rise In The Twentieth Century

Authors: Jeffry A Frieden

1st Edition

0393058085, 9780393058086

More Books

Students also viewed these Economics questions

Question

Conduct a SWOT analysis of starbuck's global strategy.

Answered: 1 week ago