A difference between the static budget based on planned volume and a flexible budget prepared at actual volume is called a: Group of answer choices
A difference between the static budget based on planned volume and a flexible budget prepared at actual volume is called a:
Group of answer choices
Flexible budget variance.
Static budget variance.
Production activity variance.
Volume variance.