a . Engineer 1 : The new building was constructed by BTC , but it was constructed according to different specifications than those approved by

a. Engineer 1: The new building was constructed by BTC, but it was constructed according to
different specifications than those approved by the municipality (e.g., using a different
engineering design). The manager of BTC informed Engineer 1 that the building was
constructed using different engineering documents than those approved by the municipality
with a lower level of safety and some design errors. A manager of BTC requests that Engineer
1 approve the building, and Engineer 1 may receive a commission from the company in the
form of advance training in certain design software.
b. Engineer 2: The electrical lighting system (ELS) of the building was not installed according to
the technical standards of the municipality. Although Engineer 2 is an electrical engineer, he is
not specialized in this particular technical standard, despite it being an electrical engineering
standard. Engineer 2 is considering approval of the electrical system despite the violation of
the municipality's code as there are no major issues with it. On the other hand, approving this
electrical system might be regarded as an act of deception in accordance with the municipal
code of conduct.
c. Engineer 3: During the inspection of the air-conditioning system (AC), it was found that the
safety short-circuit was missing. This problem may result in the AC system overheating and
resulting in the electrical wiring being burned out. BTC's manager, however, requested that
Engineer 3 not report the air conditioning system, as it is a new system with low safety risks.
Failure to report an issue with the fire system would be a violation of civil defense laws.
Engineer 3 offered to work with BTC to resolve the AC problem.
Page 1 of 4
Based on the comments of these engineers, answer the following questions. Buildings should be
approved by the three engineers in accordance with the technical regulations of the
municipality and the government.
ENGINEERING ETHICS CASE STUDY - Answer Form
For three engineers, what is the ethical dilemma in this case?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Chemical Engineering Thermodynamics

Authors: J.M. Smith, Hendrick Van Ness, Michael Abbott, Mark Swihart

9th Edition

1260721477, 978-1260721478

More Books

Students also viewed these Chemical Engineering questions

Question

What lessons in OD contracting does this case represent?

Answered: 1 week ago

Question

Does the code suggest how long data is kept and who has access?

Answered: 1 week ago