Question

1 Approved Answer

A geotechnical report provided by the owner indicated that soils excavated for a parking garage would consist of silty clays that were suitable for use

A geotechnical report provided by the owner indicated that soils excavated for a parking garage would consist of silty clays that were suitable for use as structural fill under a new building to be erected on the site. The contractor's bid relied upon using that excavate for fill. However, on performing the excavation, no silty clays were found. Shale was found instead. Because this shale was unsuitable for fill, the contractor had to purchase fill from a borrow pit and haul it onto the site at her own expense. The contractor made a site visit before bidding. The shale formation was concealed under at least one foot of top soil and could not have been discovered during that site visit. The owner-contractor agreement is silent about differing site conditions.

Is the owner responsible for the cost of the fill material?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

11th Edition

978-0324651812, 324651813, 978-0324651751

More Books

Students also viewed these General Management questions

Question

Determine whether the number is rational or irrational. 36

Answered: 1 week ago