Question

1 Approved Answer

A graphic artist agreed to create 100 new icons in 100 days at a cost of 50 QR an icon. After 25 days, the graphic

image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
A graphic artist agreed to create 100 new icons in 100 days at a cost of 50 QR an icon. After 25 days, the graphic artist had completed 22 icon at a total cost of 1,140 QR. BAC: Budget at Completion PV: Planned Value AC: Actual Cost EV: Earned Value SV: Scheduled Variance SPI: Schedule Performance Index round to 2 decimal places CPI: Cost Performance Index round to 2 decimal places EAC(BAC/CPI) Is this project under budget? Answer yes or no. Is this project on schedule? Answer yes or no. An electrician is required to install lighting fixtures in a 200 room hotel. He has to install 5 lighting fixtures in each room. The approved budget for the work is 500,000 QR and the approved schedule is 14 weeks. After 8 weeks, the electrician has completed 110 rooms and spend 250,000 QR. BAC: Budget at Completion PV: Planned Value AC: Actual Cost EV: Earned Value SV: Scheduled Variance The project is to excavate 750,000 cubic meters of dirt. According to the management plan you need to excavate 60,000 cubic meters of direct per week at a cost of 5 QR/Cubic Meter. After 9 weeks, 600,000 cubic meters of dirt has been excavated at total cost of 3,000,000 QR. BAC: Budget at Completion PV: Planned Value AC: Actual Cost EV: Earned Value SV: Scheduled Variance SPI: Schedule Performance Index round to 2 decimal places CPI: Cost Performance Index round to 2 decimal places EAC(BAC/CPI) Is this project under budget? Answer yes or no. Is this project on schedule? Answer yes or no. You are managing the construction of a new airport. The project is scheduled to be completed in 2 years with an approved budget of 30,000,000QR. At the end of the first year, the value of the work completed is 18,000,000 QR. The actual costs are 14,400,000. BAC: Budget at Completion PV: Planned Value AC: Actual Cost EV: Earned Value SV: Scheduled Variance SPI: Schedule Performance Index round to 2 decimal places CPI: Cost Performance Index round to 2 decimal places EAC(BAC/CPI) Is this project under budget? Answer yes or no. Is this project on schedule? Answer yes or no

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Pain Management Workbook

Authors: Rachel Zoffness, Mark A. Schumacher

1st Edition

1684036445, 978-1684036448

More Books

Students also viewed these General Management questions

Question

Define Internal Rate of Return (IRR).

Answered: 1 week ago