Question

1 Approved Answer

A hydro-turbine is proposed for a dam with an estimated gross head of 20.5 m and a flow rate of 4.52m 3 /s. The generator

A hydro-turbine is proposed for a dam with an estimated gross head of 20.5 m and a flow rate of 4.52m3/s. The generator is to turn at 120 rpm. You are required to identify (K5) the type of turbine best suited for this dam.For estimation purposes, set turbine = 85% and other = 95%. Note that a reasonable approximation is that net head H =turbine ×other ×Gross. The electrical generator efficiency is generator = 95%.

Scenario (A): If all the flow is to go through one turbine, calculate the turbine specific speed and then select the most appropriate type of turbine for this situation.
Scenario (B): If the flow is split into 8 identical turbines, calculate the turbine-specific speed and then select the most appropriate type of turbine for this situation.

Step by Step Solution

3.43 Rating (150 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Chemical Engineering Thermodynamics

Authors: J. M. Smith, H. C. Van Ness, M. M. Abbott

7th edition

71247084, 978-0071247085

More Books

Students also viewed these Mechanical Engineering questions