A manufacturing company is planning to use PERT to setup a project for a new production line. For this project, they have established the

  

A manufacturing company is planning to use PERT to setup a project for a new production line. For this project, they have established the following activities, precedence relationships. and time estimates in days: Activity Immediate Duration Predecessors (Days) A 10 B 7 C B 3 D A 15 E D 7 F C 10 G D 7 H EF 15 (a) What is the expected duration for activity "b"? (b) What is the variance of activity "d"? (c) How many paths are there in the network? (d) What is the earliest finish (EF) time for activity "e"? (e) What is the slack in days for activity "c"? (f) What is the critical path? (g) What is the duration of the critical path in days?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

a Expected duration for activity B For activity B the immediate predecessors are activities C and D Therefore the expected duration of B is the sum of ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Financial Management

Authors: James R Mcguigan, R Charles Moyer, William J Kretlow

10th Edition

978-0324289114, 0324289111

More Books

Students also viewed these Mathematics questions