A manufacturing company is planning to use PERT to setup a project for a new production line. For this project, they have established the
A manufacturing company is planning to use PERT to setup a project for a new production line. For this project, they have established the following activities, precedence relationships. and time estimates in days: Activity Immediate Duration Predecessors (Days) A 10 B 7 C B 3 D A 15 E D 7 F C 10 G D 7 H EF 15 (a) What is the expected duration for activity "b"? (b) What is the variance of activity "d"? (c) How many paths are there in the network? (d) What is the earliest finish (EF) time for activity "e"? (e) What is the slack in days for activity "c"? (f) What is the critical path? (g) What is the duration of the critical path in days?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
a Expected duration for activity B For activity B the immediate predecessors are activities C and D Therefore the expected duration of B is the sum of ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3