Question

1 Approved Answer

A medium-size municipality plans to develop a software system to assist in project selection during the next 10 years. A life-cycle cost approach has been

  • A medium-size municipality plans to develop a software system to assist in project selection during the next 10 years. A life-cycle cost approach has been used to categorize costs into development, programming, operating, and support costs for each alternative. There are three alternatives under consideration, identified as A (tailored system), B (adapted system), and C (current system). Find the annual worth of life-cycle cost for the best alternative at 8% per year.

Alternative

Component

Cost

A

Development

$925,000 now, $370,000 years 14

Programming

$925,000 now, $740,000 years 1, 2

Operation

$185,000 years 110

Support

$185,000 years 15

B

Development

$185,000 now

Programming

$370,000 year 0, $185,000 years 13

Operation

$370,000 years 110

Support

$370,000 years 110

C

Operation

$925,000 years 110

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Concept Audits A Philosophical Method

Authors: Nicholas Rescher

1st Edition

1498540392, 978-1498540391

More Books

Students also viewed these Accounting questions

Question

Ensure that meetings lead to action.

Answered: 1 week ago