Question
A Multi-Part Question: The engineers at Cyberdyne Corporation have developed a new robotic manufacturing machine, the Model T1000.The marketing department's forecast for sales of the
A Multi-Part Question:
The engineers at Cyberdyne Corporation have developed a new robotic manufacturing machine, the Model T1000.The marketing department's forecast for sales of the new machine are shown below.The equipment needed to manufacture the machine is expected to have a useful life of 9 years.The equipment will be installed on January 1, 2020 and the project will commence operations in 2020.
Revenue Forecast for the Model T1000
($ In Thousands)
Year:
2020
2021
2022
2023
2024
2025
2026
2027
2028
Revenue:
$1900
$2100
$2500
$2700
$2900
$3000
$2800
$2500
$2100
The following information has also been provided:
1.Management estimates the equipment and other assets needed to manufacture and distribute the T1000 will cost $2,500,000.The assets have an MACRS class life of 7 years and will have a salvage value of $300,000 at the end of the project.The equipment would be installed at the end of 2018 and production would begin in 2019.Assume the MACRS system is used to determine depreciation.
MACRS Depreciation Rates for 7 Year Class Life
Year:
1
2
3
4
5
6
7
8
Revenue:
14%
25%
17%
13%
9%
9%
9%
4%
2.Based on the forecast volume of production, management forecasts the raw materials cost schedule shown below.
Forecast of Cost of Raw Materials and Parts
($ In Thousands)
Year:
2020
2021
2022
2023
2024
2025
2026
2027
2028
Materials Cost:
$900
$1000
$1100
$1300
$1350
$1400
$1350
$1250
$1200
3.Miscellaneous expenses and other costs are shown below:
Forecast of Miscellaneous Expenses and Other Costs
($ In Thousands)
Year:
2020
2021
2022
2023
2024
2025
2026
2027
2028
Other Costs:
$300
$350
$400
$425
$500
$550
$600
$650
$700
4.Cyberdyne's income tax rate is 35%.
5.The company generally requires net working capital to be 25% of sales.
6.Because Cyberdyne has signed long-term agreements for raw materials, the investment is considered to be less risky than the average investment.One way of taking risk into account is to have a higher or lower discount rate, or required rate of return.Consequently, Cyberdyne requires a minimum rate of return of 6.75% on this project.
Questions:
28.The Initial Investment of the Project, or the Cash Outflow at time zero at the end of 2019, is:
a.$1075
b.$1575.
c.$2025
d.$2500.
e.$2975.
29.The project's free cash flows for the first three years, or years 2020, 2021, and 2022, are:
202020212022
a.$350$125$575
b.$228$81$374
c.$528$606$749
d.$578$706$799
e.$805$1,113$1,075
30.The project's free cash flows for the second three years, or years 2023, 2024, and 2025, are:
202320242025
a.$423$536$536
b.$748$761$761
c.$650$825$825
d.$698$736$811
e.$959$908$908
31.The project's free cash flows for the final three years, or years 2026, 2027, and 2028, are:
202620272028
a.$406$325$130
b.$631$425$130
c.$778$490$130
d.$625$500$500
e.$706$525$850
32.The projects cash flow from salvage is:
a.$300
b.$295
c.$195
d.$105
e.$720
33.The project's Net Present Value is:
a.$4,489
b.$2,188
c.$1,514
d.($678)
e.($787)
34.After completing the analysis, you are informed by suppliers of the special metals and electrical components needed for production of the new machine will qualify Cyberdyne for quantity discounts.The forecast is that the discounts will reduce the cost of raw materials and supplies used in all of Cyberdyne's products by $300,000 annually during the life of the project.The cost reduction is an example of:
a.an opportunity cost.
b.a sunk cost.
c.a negative externality.
d.a synergy or positive externality.
e.a real option.
35.Taking the $300,000 annual quantity discounts into account, the project's free cash flows for the first three years, or years 2020, 2021, and 2022, are:
202020212022
a.$650$425$875
b.$528$381$674
c.$723$801$944
d.$773$901$994
e.$1,000$1,308$1,270
36.The project's free cash flows for the second three years, or years 2023, 2024, and 2025, are:
202320242025
a.$723$836$836
b.$1,048$1,061$1,061
c.$845$1,020$1,020
d.$893$931$1,006
e.$1,154$1,103$1,103
37.The project's free cash flows for the final three years, or years 2026, 2027, and 2028, are:
202620272028
a.$601$520$325
b.$826$620$325
c.$973$685$325
d.$820$695$695
e.$901$720$1,045
38.The project's Net Present Value would now be:
a.$5,773
b.$4,164
c.$2,798
d.$1,189
e.$606
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started