Question

1 Approved Answer

A new Civil Engineer failing to complete his contract worth 70000 pesos in a specified time is compelled to pay the penalty of 1/2 of

A new Civil Engineer failing to complete his contract worth 70000 pesos in a specified time is compelled to pay the penalty of 1/2 of 1% per day for the first 6 days of the extra time required, and for each additional day thereafter, the stipulated penalty is increased by 10% of 35.00 each day. If he pays a total penalty of 6160 pesos, by how many days did he overrun his contact time?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Economics A Problem-Solving Approach

Authors: Luke M. Froeb, Brain T. Mccann

2nd Edition

B00BTM8FK0

More Books

Students also viewed these Economics questions

Question

How do books become world of wonder?

Answered: 1 week ago

Question

If ( A^2 - A + I = 0 ), then inverse of matrix ( A ) is?

Answered: 1 week ago

Question

LO10.2 List the conditions required for purely competitive markets.

Answered: 1 week ago