Question
A new client has come to the office with a set of plans for a 3,000 sq. ft. house (on two levels including the 8'
A new client has come to the office with a set of plans for a 3,000 sq. ft. house (on two levels including the 8' basement foundation) in your community. They already have their lot which has a small one-story teardown on it. The lot has easy access from the front only. Our interim price for the construction of the house has been accepted (before the building permit). We are going to perform the demolition and cleanup on the property on a cost-plus basis.
The following items provide details about the property.
- Lot size is 60' by 120' serviced by city water and sewer.
- There are several large cedar and fir trees on the property; some may be in the way of the new construction
- The design used an existing survey that is 45 years old
- There may be an old septic tank and possibly a heating oil tank on the lot based on the old survey
- The property to the back of this property has an old garage on it that encroaches onto your client's property by 5 feet
- Plans have not been submitted for a building permit
INSTRUCTIONS
Describe the tasks you would be required to perform in your community to successfully bring this project to completion of the poured foundation. Consider the items listed in the guidelines and elaborate where you feel necessary. Use enough detail to allow the instructor to determine your grasp of the assignment.
Note these are listed in no specific order of importance. This list can and should be added to where applicable.)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Outline what you believe will be required to successfully achieve this phase of the project (completion of poured foundation). You are expected to have a minimum of ¾ of a page of information here. You can use a bullet point format.
Example: Parking - list all required information
STEP TWO
Supply an itemized schedule (Tasks) for the building of the entire house from the ground up (turn-key) with approximate timing for each (Duration). Be sure to include all the major parties that will be involved. If you already use a scheduling system you can supply a formal schedule from your program. (MS Project or Excel spreadsheet etc.) Don't worry about weekends or holidays - for ease, create a continuous timeline.
Items that must be included:
An itemized schedule of events including tasks, duration, and timelines.
- Include the many different parties that will be involved in the project. i.e. engineer(s), trades, etc
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started