A painter completes the application of the primer coat at 8:00 a.m. If the coating requires a 5 hour delay before recoating, at what time
A painter completes the application of the primer coat at 8:00 a.m. If the coating requires a 5 hour delay before recoating, at what time can the painter begin to apply the next coat? A. 11:00 a.m. B. 12:00 p.m. C. 1:00 p.m. D. 2:00 p.m