Siteraze Ltd is a company which engages in site clearance and site preparation work. Information concerning its operations is as follows: (i) It is company

Siteraze Ltd is a company which engages in site clearance and site preparation work. Information concerning its operations is as follows:

(i) It is company policy to hire all plant and machinery required for the implementation of all orders obtained, rather than to purchase its own plant and machinery.

(ii) Siteraze Ltd will enter into an advance hire agreement contract for the coming year at one of three levels — high, medium or low, which correspond to the requirements of a high, medium or low level of orders obtained.

(iii) The level of orders obtained will not be known when the advance hire agreement contract is entered into. A set of probabilities have been estimated by management as to the likelihood of the orders being at a high, medium or low level.

(iv) Where the advance hire agreement entered into is lower than that required for the level of orders actually obtained, a premium rate must be paid to obtain the additional plant and machinery required.

(v) No refund is obtainable where the advance hire agreement for plant and machinery is at a level in excess of that required to satisfy the site clearance and preparation orders actually obtained.

A summary of the information relating to the above points is as follows:

Plant and machinery hire costs

Level of

Advance

Conversion

orders

Turnover

Probability

hire

premium

(£000)

(£000)

(£000)

High

15000

0.25

2300

Medium

8 500

0.45

1500

Low

4 000

0.30

1000

Low to medium

850

Medium to

high

1300

Low to high

2150

Variable cost (as a percentage of turnover) 70%

Required: Using the information given above:

(a) Prepare a summary that shows the forecast net margin earned by Siteraze Ltd for the coming year for each possible outcome.

(b) On the basis of maximizing expected value, advise Siteraze whether the advance contract for the hire of plant and machinery should be at the low, medium or high level.

(c) Explain how the risk preferences of the management members responsible for the choice of advance plant and machinery hire contract may alter the decision reached in (b) above.

(d) Siteraze Ltd is considering employing a market research consultant who will be able to say with certainty in advance of the placing of the plant and machinery hire contract, which level of site clearance and preparation orders will be obtained. On the basis of expected value, determine the maximum sum which Siteraze Ltd should be willing to pay the consultant for this information.

Step by Step Solution

3.58 Rating (155 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles of Cost Accounting

Authors: Edward J. Vanderbeck, Maria Mitchell

17th edition

9781305480520, 1305087402, 130548052X, 978-1305087408

More Books

Students also viewed these Accounting questions

Question

Explain possible uses for single-case research.

Answered: 1 week ago