A production process at Kenneth Day Manufacturing is shown in Figure S7.9. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding

A production process at Kenneth Day Manufacturing

is shown in Figure S7.9. The drilling operation occurs separately

from, and simultaneously with, the sawing and sanding operations.

A product needs to go through only one of the three assembly

operations (the operations are in parallel).

a) Which operation is the bottleneck?

b) What is the bottleneck time?

c) What is the throughput time of the overall system?

d) If the firm operates 8 hours per day, 20 days per month, what

is the monthly capacity of the manufacturing process?

Sawing 6 units/hr

sanding 6 unity/hr

drilling 2.4 units/hr

all going into welding 2 unitys/hr

than from that goes

assembly 0.7 unity/hr

assembly 0.7 units/hr

assembly 0.7 unity/hr

so there are three assembly areas

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

M Finance

Authors: Marcia Cornett, Troy Adair, John Nofsinger

3rd Edition

0077861779, 978-0077861773

More Books

Students also viewed these Finance questions

Question

1. Identify three approaches to culture.

Answered: 1 week ago

Question

2. Define communication.

Answered: 1 week ago

Question

4. Describe how cultural values influence communication.

Answered: 1 week ago