A project being analyzed by PERT has 4 5 activities, 2 5 of which are on the critical path. If the estimated time along the

A project being analyzed by PERT has 45 activities, 25 of which are on the critical path. If the estimated time along the critical path is 400 days with a project variance of 120, what is the probability that the project will be completed in 420 days or less?
Selected Answer:
0.9660
Answers:
0.9660
0.9770
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Risk Management and Insurance

Authors: Mark S. Dorfman, David Cather

10th edition

131394126, 978-0133255409, 133255409, 978-0131394124

More Books

Students also viewed these General Management questions

Question

1. With regard to Emma, what sales training needs can you identify?

Answered: 1 week ago