A project has a budget of $5,000 and Earned Value of $2,000. The Cost Performance Index is 1.1. The plan was to have 50% of
A project has a budget of $5,000 and Earned Value of $2,000. The Cost Performance Index is 1.1. The plan was to have 50% of the work completed by now.
If the variances are atypical, what is the Estimate at Completion?
If the project must meet the deadline, what is the Estimate at Completion?
What is the To Complete Performance Index for finishing the project within the $5,000 budget?
What does this TCPI tell us?