A project has the following financial details: Budgeted Costs: $800,000 Actual Costs: $850,000 Planned Value (PV): $770,000 Earned Value (EV): $760,000 Questions: Calculate the Cost
A project has the following financial details:
- Budgeted Costs: $800,000
- Actual Costs: $850,000
- Planned Value (PV): $770,000
- Earned Value (EV): $760,000
Questions:
- Calculate the Cost Variance (CV) and Schedule Variance (SV).
- Determine the CPI and SPI.
- Discuss what these financial ratios indicate about the project’s performance.