Question

1 Approved Answer

A project has the following forecasted cash flows: Cash Flows ($ thousands) C 0 C 1 C 2 C 3 130 +70 +90 +80 The

A project has the following forecasted cash flows:

Cash Flows ($ thousands)
C0 C1 C2 C3
130 +70 +90 +80

The estimated project beta is 1.56. The market return rm is 18%, and the risk-free rate rf is 3%.

a. Estimate the opportunity cost of capital and the projects PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands. Round your answers to 2 decimal places.)

Cost of capital %
PV $

b. What are the certainty-equivalent cash flows in each year? (Do not round intermediate calculations. Enter your answers in thousands rounded to 2 decimal places.)

Year Certainty-Equivalent Cash Flow
1 $
2 $
3 $

c. What is the ratio of the certainty-equivalent cash flow to the expected cash flow in each year? (Do not round intermediate calculations. Round your answers to 4 decimal places.)

Year Ratio
1
2
3

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: Belverd E Needles, Marian Powers

10th Edition

0547193289, 9780547193281

More Books

Students also viewed these Finance questions