A project has the following information (FS dependencies). What is the duration of the critical path? (5 marks) (Hint: you do not need to do
A project has the following information (FS dependencies). What is the duration of the critical path? (5 marks) (Hint: you do not need to do a forward and backward pass) What is the probability in completing the project between 23 and 33 time periods? (15 Marks) Optimistic Most Likely Pessimistic Activity Time Time Time Predecessors A 2 6 B 2 5 8 A C 3 4 A D 1 A F B,C 2 B,C,D G F H 11 E, G