A project has three critical paths: A-B-C-D-E, A-G-H-E, and A-F-I-E. Crashing costs (in thousands, per week) for each activity is listed below: Activity Crashing 1st
A project has three critical paths: A-B-C-D-E, A-G-H-E, and A-F-I-E. Crashing costs (in thousands, per week) for each activity is listed below:
Activity | Crashing 1st time | Crashing 2nd time | Crashing 3rd time |
A | 44 | 1 | 4 |
B | 25 | 2 | 1 |
C | 39 | 4 | 2 |
D | 8 | 10 | 2 |
E | 34 | 4 | 3 |
F | 33 | 30 | 3 |
G | 34 | 12 | 2 |
H | 4 | 8 | 3 |
I | 4 | 8 | 4 |
What is the total cost of reducing this project by two weeks?
42
b.78
c.60
d.50
e.35
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started