Question

1 Approved Answer

A project has three critical paths: A-B-C-D-E, A-G-H-E, and A-F-I-E. Crashing costs (in thousands, per week) for each activity is listed below: Activity Crashing 1st

A project has three critical paths: A-B-C-D-E, A-G-H-E, and A-F-I-E. Crashing costs (in thousands, per week) for each activity is listed below:

Activity Crashing 1st time Crashing 2nd time Crashing 3rd time
A 44 1 4
B 25 2 1
C 39 4 2
D 8 10 2
E 34 4 3
F 33 30 3
G 34 12 2
H 4 8 3
I 4 8 4

What is the total cost of reducing this project by two weeks?

42

b.78

c.60

d.50

e.35

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Information Technology

Authors: Carol Brown, Daniel DeHayes, Jeffrey Hoffer, Wainright Marti

7th Edition

132146320, 978-0132146326

More Books

Students also viewed these General Management questions