A project manager had originally planned to use both of the company's industrial 3 D printers simultaneously for the training mock - up project but
A project manager had originally planned to use both of the company's industrial D printers simultaneously for the training mockup project but has just learned that one of them will be unavailable. The project manager adjusts the schedule so that the components are created sequentially using the one remaining D printer. Unfortunately, this action affects the critical path and delays the planned finish date of the project. What tool or technique has the project manager used in this situation?
Group of answer choices
Crashing
Resource smoothing
Fast tracking
Resource leveling
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started