Question

1 Approved Answer

A project manager has collected the following information for her new software application project to generate a customer database. Activity ID Activity Description Predecessor Duration

A project manager has collected the following information for her new software application project to generate a customer database.

Activity ID Activity Description Predecessor Duration (Day)
Optimistic Most Likely Pessimistic
A Systems design - 6 8 10
B Subsystem A design A 1 2 3
C Subsystem B design A 1 3 5
D Subsystem C design A 40 60 80
E Program A B 30 40 50
F Program B C 1 2 3
G Program C D 1 2 3
H Subsystem A test E, F 15 20 25
I Subsystem B test G 5 10 15
J Subsystem C test H, I 5 10 15
K Integration J 6 12 18
L Integration test K 1 3 5

  1. a) Develop the project network diagram.
  2. b) Complete the forward and backward pass, and compute activity slack. Use PERT techniques for project activities duration.
  3. c) Compute the project duration and identify the critical path.
  4. d) Compute the probability the project will be done in 108 days.
  5. e) With a probability of 90%, how long does the project take?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Leading Strategic Change In An Era Of Healthcare Transformation

Authors: Jim Austin ,Judith Bentkover ,Laurence Chait

1st Edition

3319808826, 978-3319808826

More Books

Students also viewed these General Management questions