A project manager is meeting with her project sponsor and selected stakeholders to determine cost thresholds, formats and frequencies for budget reports, and a procedure
A project manager is meeting with her project sponsor and selected stakeholders to determine cost thresholds, formats and frequencies for budget reports, and a procedure for recording costs during the project. The project manager also decides to consult with the organization's legal and finance teams to uncover any factors that may affect their decision to use overseas vendors. What is the output of the process described above
Step by Step Solution
There are 3 Steps involved in it
Step: 1