A project manager is overseeing a project with a total budget of $6,000,000. The project is halfway through its timeline with the following costs incurred:
A project manager is overseeing a project with a total budget of $6,000,000. The project is halfway through its timeline with the following costs incurred:
- Actual Costs to Date: $3,000,000
- Planned Value to Date: $3,200,000
- Earned Value to Date: $2,800,000
Questions:
- Calculate the Cost Performance Index (CPI) and Schedule Performance Index