Question

1 Approved Answer

A project manager surveyed his earned value table at the conclusion of month 24 The results are shown in the table below. ($ values shown)

image text in transcribed
A project manager surveyed his earned value table at the conclusion of month 24 The results are shown in the table below. ($ values shown) The planned payment schedule is shown with % Complete which can be used to calculate earned value for each activity. Pay attention to the Actual Costs (payments). Copy the table below into Excel and show your work by expanding or adding the necessary rows and columns and then add a small table at below the main table for the Calculate the Total Budget at Completion (BAC) for the project Calculate the Schedule Variance and the SPI for this project at the end of the 24th month Calculate the Cost Variance and the CPI for the project at the end of the 24th month Calculate the Estimate at Completion Is the project on budget / over budget / under budget? What is showing you this? What might this mean in terms of upcoming payments for this project? Is the project on schedule / ahead of schedule / behind schedule? What is showing you this? How do you feel overall about the way this project is proceeding? What would you report to the project sponsor? Submit the result as a single MS Excel spreadsheet with your name in cell Al and your student number in cell B1 Activity 4 8 12 16 20 24 28 TOTAL % Complete Concept Design $500 $1,500 $2,000 $3,000 $3,000 $1,500 $11,500 85% Proposal $450 $4,500 $100 $100 $4,500 $9,650 90% Negotiations $500 $1,200 $1,700 100% Resource Acquisition $500 $500 100% Training $300 $750 $950 $2,000 100% Modeling $400 $1,000 $1,400 75% Planning $2,000 $500 $3,000 $2,000 $7,500 60% Testing $500 $500 $1,000 $4,000 $6,000 10% Control $1,200 $2,000 $3,200 30% Quality Assurance $100 $500 $500 $500 $500 $3,500 $5,600 50% Scope Verification $1,000 $1,000 $6,000 $8,000 30% Contract Closure $2,000 $4,000 $6,000 40% Total Cumulative Total Actual Cost $500 $5,000 $11,000 $5,500 $8,000 $8,000 Cumulative Actual Cost

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quality Management In Construction Projects

Authors: Abdul Razzak Rumane

2nd Edition

0367890038, 978-0367890032

More Books

Students also viewed these General Management questions

Question

What is one of the skills required for independent learning?Explain

Answered: 1 week ago