A project network has the following activity details. If Activity D is delayed by 4 weeks beyond its estimated duration, which of the following will
A project network has the following activity details. If Activity D is delayed by weeks beyond its estimated duration, which of the following will be true?
Group of answer choices
Activity D will then have slack of one week
Activity E will start to have a slack
Activity D will be on the critical path
Activity G will no longer be on the critical path.