Question
A project requires the tasks shown below to be completed. The duration column shows the number of weeks estimated for one person to complete the
A project requires the tasks shown below to be completed. The duration column shows the number of weeks estimated for one person to complete the task.
Task | Duration | Depends on |
T1 | 1 | |
T2 | 3 | |
T3 | 5 | |
T4 | 3 | T1 |
T5 | 2 | T1 |
T6 | 2 | T1,T3 |
T7 | 1 | T2,T3 |
T8 | 3 | T4,T5,T6 |
T9 | 3 | T5,T7 |
T10 | 2 | T7 |
T11 | 2 | T8 |
T12 | 3 | T8,T9 |
T13 | 2 | T10 |
answer the questions below. These activities are intended to develop and assess your understanding of the method, so please do not use a software project management tool such as Microsoft Project to assist in either drawing the diagrams or in computing solutions.
Questions :
=> List or otherwise indicate the task on the critical path and compute its length,
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started