Question
A Scrum team would like to defer creating Acceptance Criteria until after they've implemented the associated User Story. Why do many Scrum proponents discourage this
A Scrum team would like to defer creating Acceptance Criteria until after they've implemented the associated User Story. Why do many Scrum proponents discourage this approach?
Defining Acceptance Criteria prior to the sprint provides an opportunity to validate the story's correct behavior with the Customer (i.e., the team can know if they are on the right track). | ||||||||||||||||||||||||||||||||
Acceptance Criteria can only be defined after the Team knows how the code works | ||||||||||||||||||||||||||||||||
Defining Acceptance Criteria prior to the sprint reduces the Team's velocity | ||||||||||||||||||||||||||||||||
Defining Acceptance Criteria prior to the sprint can improve the story's estimate | ||||||||||||||||||||||||||||||||
Defining Acceptance Criteria prior to the sprint improves the Team's planning of what Tasks are required to implement the User Story
Which of the following activities occur during the Sprint Planning meeting?
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started