A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown
A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown in the following table.
tableActivityTime,Immediate PredecessorA find client,B write prospectus,AC obtain approval from client and professor,BD complete programming,CE do industry background research,F write final paper,D EG write oral report,D E
Both written and oral reports are required. Draw the project network. Can they complete the project in the class days remaining until the end of the semester?
they can complete it in time since the project is expected to be completed in days.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started