Question

1 Approved Answer

A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown

A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown in the following table.
\table[[Activity,Time,Immediate Predecessor],[A. find client,5,],[B. write prospectus,3,A],[C. obtain approval from client and professor,5,B],[D. complete programming,13,C],[E. do industry background research,10,],[F. write final paper,7,D, E],[G. write oral report,5,D, E]]
Both written and oral reports are required. Draw the project network. Can they complete the project in the 44 class days remaining until the end of the semester?
, they can complete it in time since the project is expected to be completed in days.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: Jay Heizer, Barry Render

11th edition

9780132921145, 132921146, 978-0133408010

More Books

Students also viewed these General Management questions