A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both
A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. How many days are required to complete the project? Select one: a. 42 days b. 11 days c. 22 days d. 27 days
A project consists of five activities. Naturally the paint mixing precedes the painting activities. Also, both ceiling painting and floor sanding must be done prior to floor buffing. Activity Floor sanding Paint mixing Wall painting Ceiling painting Floor buffing Select one: Optimistic Time (hr) a. 1.14 O b. 1.07 0 c. 1.30 O d. 3.03 3 0.5 1 1 1 Most Probable Time (hr) 4 1 What is the standard deviation of the expected completion time? 2 5.5 2
Step by Step Solution
★★★★★
3.41 Rating (148 Votes )
There are 3 Steps involved in it
Step: 1
Quiz a Answer is c 130 explain with calculations The expected completion ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started