A single model assembly lime is being planned to produce a consumer appliance at the rate of 9 0 . 0 0 0 units year

A single model assembly lime is being planned to produce a consumer appliance at the rate of 90.000 units year The line will be operated at 50 weeks year, 5 shifts/week, and 6 hours/shift There will be one worker per station. Previous experience suggests that the uptime efficiency for the line will be 100% and there is no repositioning time. The work elements, their times and
precedence consuaints are given in the table below
Determime
a) Hourly Production Rste
b) Cyde Time
c) Theorical minimum number of workas
d) Service time to which the line must be balanced
e) Deemine an effent line balancing solution using ranked positional weights method delamine the balance delay

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Optimization Of Logistics And Supply Chain Systems Theory And Practice

Authors: Turkay Yildiz

1st Edition

1540716198, 978-1540716194

More Books

Students also viewed these General Management questions