Question
1 Approved Answer
The cement contractor is scheduled to pour the cement on 15th of March. They cannot do it sooner or later. This is an example of
- The cement contractor is scheduled to pour the cement on 15th of March. They cannot do it sooner or later. This is an example of
- Start to Finish
- Constraint
- Dependency
- Finish to Start
- The image below indicates:
- Start to start dependency between L and J
- Finish to finish dependency between L and J
- Start to finish dependency between L and J
- Finish to start dependency between L and J
- Developers are accountable for what?
- Adapting their plan to Spring Goal
- Holding each other professional
- All of the other answers
- The Sprint Plan
- Dependency means some activity's start or finish is dependent on another activity
- True False
- The following is a good milestone section for the project charter:
Project Start
Planning the project
Making prototype
Finalizing the design
Development
Project Fisnish
- True
- False
- Projects, programs, subsidiary portfolios, and operations is called
- Projects
- Program
- Portfolio
- Process
- Project manager role in traditional project management is exactly the same as the role of Scrum master in Scrum framework.
- True
- False
- In lessons learned meeting we try to get to the root cause of the issues.
- True
- False
- Who most likely creates the Business case?
- Customer
- Product manager
- Team members
- Project manager
- During the closing phase a project plan can be used to assess project success.
- True
- False
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started